Fleet Strength of Indian Navy
Government constantly reviews the security environment and decides
about induction of appropriate defence
equipment/platforms, including various kinds of ships/submarines for the Navy.
This is a continuous process undertaken as per the Defence Procurement
Procedure (DPP) from various indigenous as well as foreign sources for the
modernization of armed forces to keep them in a state of readiness to meet any
eventuality. Proposals for induction of naval ships are based on the Maritime
Capability Perspective Plan (MCPP)/Five Year Plan/Annual Plan which stipulates
the number and type of vessels required as well as timelines for such
inductions. Divulging further details would not be in the national interest.
Major warship construction projects of the Navy running behind
schedule include Project-15A (P-15A) and Project-17 (P17). The cost escalation
in these two projects has been about 225% and 260% respectively. The major cost
escalation & delay has been due to uncertainties associated with the
complex warship building process. Reasons for delay and cost escalations in
respect of P-15A and P-17 are as follows:
P-15A: The main reasons contributing towards cost escalations are -
delay in supply of warship building quality steel by Russia, escalation due to
increase in expenditure towards services of Russian Specialists on account of
inflation during the build period, impact of Wage revision due from October
2003 and finalization of cost of weapons and sensors.
P-17: The main reasons contributing towards cost escalations are -
delay in supply of warship building quality steel by Russia, delay in
acquisition of weapon equipment from Russia, and delay in finalization of propulsion
equipment in view of complex combined diesel and gas arrangement introduced for
the first time in Indian Navy frigate.
A contract was signed with Rosoboronexport, Russia in 2006 for
acquisition of three Talwar Class follow-on ships and the delivery schedule for
these three ships was April 2011, October 2011 and April 2012. Rosoboronexport
has intimated that the delivery of the ships would be delayed as follows: 1st
Ship - 12 months, 2nd Ship - 11 months and 3rd Ship - 14 months. The contract
for acquisition of these three ships is a fixed price contract.
A programme for construction of six Scorpene submarines is currently
underway at M/s. Mazagon Dock Limited (MDL) under Project- 75. As per the
contract, the 1st submarine was scheduled to be delivered in December 2012 and
thereafter, one each every year till December 2017. There has been delay in
this project due to initial teething problems, absorption of complex
technology, augmentation of MDL infrastructure and procurement of MDL Purchased
Material (MPM). The 1st submarine is now scheduled to be delivered in the
second half of 2015.
Acceptance of Necessity for acquisition of Six Submarines under
Project-75 (India) has been accorded by the Defence Acquisition Council. The
proposal is being progressed. A modernization programme has been initiated for
the existing submarine fleet and a number of platforms have already been
modernized. The programme has been worked out by the Navy catering to the
obsolescence/non- supportability of system/equipment and to include
contemporary technology.
During the last five years, construction of three ships under P-17,
three ships under P-15A and four ships under P-15B has been assigned to MDL.
The 1st ship and the 2nd ship under P-17 have been commissioned in April 2010
and August 2011 respectively and the 3rd ship is expected to be commissioned in
early 2012. The three ships under P-15A are scheduled to be delivered by March
2012, March 2013 and March 2014 respectively. Contract for four P-15B ships has
been signed in January 2011, with delivery schedule as July 2018, July 2020,
July 2022 and July 2024 respectively. There is no proposal at present for
creation of MDL facilities at Mangalore. This information was given by Defence
Minister Shri AK Antony in a written reply to Shri K Shivakumar and others in
Lok Sabha today. [Press Information Bureau Report].
|